I built a set up on a place I managed in Alabama for game feeders that allowed one person to fill 7 ton feeders by himself in less than 45 minutes. We bought 7 ton creep feeders on wheels and modified em to feed wide antlered bucks. Then built tin topped concrete slabs to park em on to keep em clean and dry. Silos at the barn to hold feed and corn with augers to fill the creep feeders that could be pulled with the tractor into place and returned to their respective slabs.
feeder on slab before top put up
feeder in place under finished cover
modifications to feeder to feed deer
20 ton silos at the barn being filled by tanker truck
we had four feeders on the property and one person could fill all four in way less than a day by himself.
feeder on slab before top put up
feeder in place under finished cover
modifications to feeder to feed deer
20 ton silos at the barn being filled by tanker truck
we had four feeders on the property and one person could fill all four in way less than a day by himself.