Well not exactly the garage, but my building floor. I have a 32x28 building that was built in 2 sections. The back part of the slab is 1.5" higher than the rest. Its cracking on the front half and the back half.
It looks like a monolithic pour (front half anyways). Any ideas on how to replace the concrete? Is it ok to cut out the center and re-pour? The city wont let me take down the whole building and start fresh without rezoning, then applying for a special use permit. Back in 1993 they decided to rezone my whole area from 1 acre lots to 8700sqft lots.
It looks like a monolithic pour (front half anyways). Any ideas on how to replace the concrete? Is it ok to cut out the center and re-pour? The city wont let me take down the whole building and start fresh without rezoning, then applying for a special use permit. Back in 1993 they decided to rezone my whole area from 1 acre lots to 8700sqft lots.