    Barndo Question for construction guys

    I am looking at building/ having built a barndo. My plan is doing it in stages over several years so I can pay for it up front.

    year 1, dirt work, any plumbing for slab, and pour slab.
    year2, shell erection
    year 3 and 4, build of inside.

    My main concern is if its ok to pour and wait a year to get cover on it. I plan on staining concrete for flooring.

    Thanks for any insight or advice.

    #2
    I dont see personally why waiting a year would be a problem. Gives it plenty of time to settle. Think of a concrete drive way....... Sits in the weather its whole life. Keep an eye out for puddling water and just push it off the slab, other than that, i think your fine

    Comment


      #3
      Originally posted by forced-2-work View Post
      I dont see personally why waiting a year would be a problem. Gives it plenty of time to settle. Think of a concrete drive way....... Sits in the weather its whole life. Keep an eye out for puddling water and just push it off the slab, other than that, i think your fine


      That's my line of thinking also, but I am not a construction guy. So ... Main question is will the elements affect the staining process a year later.

      Comment


        #4
        Originally posted by one66stang View Post
        That's my line of thinking also, but I am not a construction guy. So ... Main question is will the elements affect the staining process a year later.
        I would pressure wash and clean the hell out of it before adding the shell. That way when staining time comes, the concrete is ready to go.

        Comment


          #5
          That was my original plan for a place down on the coast, but things kinda happened different thanks to Harvey and I did the slab and shell at once.

          As to your concern, the guys I talked to said it shouldn't matter for the staining as they'll have to clean it real good first anyway. Might make a difference if your parking on it, or have something natural leaching into it.

          Originally posted by one66stang View Post
          I am looking at building/ having built a barndo. My plan is doing it in stages over several years so I can pay for it up front.

          year 1, dirt work, any plumbing for slab, and pour slab.
          year2, shell erection
          year 3 and 4, build of inside.

          My main concern is if its ok to pour and wait a year to get cover on it. I plan on staining concrete for flooring.

          Thanks for any insight or advice.