Scenario:
we are building a flagstone patio in our backyard, first a slab poured and then flagstone to be layed over it.
we were pouring concrete today and ran into a very unforeseen delay and the end result being we only got about 80 sq.ft of concrete poured out of a 500 sq. slab. Slab has wire mesh , rebar around the footing and along the home as well as being doweled into the slab with the exception of the existing slab (9x10 surface pad which I chose not to dowel into because of its 3-4" thickness, was afraid of cracking or other issues, this is where the 80 sq. section was poured)
anyway, due to the delay we are now going to have a cold joint....there was no joint placed where it ends, just kind of tapers off.
do anyone with more experience than me foresee an issue with this? I was planning on having them throw in some more mesh and dowel into where it end to the new pour and then finish it off.
thanks for the response
we are building a flagstone patio in our backyard, first a slab poured and then flagstone to be layed over it.
we were pouring concrete today and ran into a very unforeseen delay and the end result being we only got about 80 sq.ft of concrete poured out of a 500 sq. slab. Slab has wire mesh , rebar around the footing and along the home as well as being doweled into the slab with the exception of the existing slab (9x10 surface pad which I chose not to dowel into because of its 3-4" thickness, was afraid of cracking or other issues, this is where the 80 sq. section was poured)
anyway, due to the delay we are now going to have a cold joint....there was no joint placed where it ends, just kind of tapers off.
do anyone with more experience than me foresee an issue with this? I was planning on having them throw in some more mesh and dowel into where it end to the new pour and then finish it off.
thanks for the response
Comment